Compute Metric Tons (MT), Brass (100 Cu.Ft), and Cubic Meters (m³) For Civil Construction
Input dimensions of your RCC slab, footing, road base, or wall to calculate exact requirement in Metric Tons, Brass, and Cubic Meters.
Use this guideline table to cross-check nominal mix volume proportions per cubic meter of concrete.
| Grade | Proportion (Cement : Sand : Aggregate) | Characteristic Strength | Recommended Structural Use |
|---|---|---|---|
| M15 | 1 : 2 : 4 | 15 N/mm² @ 28 Days | PCC, Leveling course, Footpath |
| M20 | 1 : 1.5 : 3 | 20 N/mm² @ 28 Days | Standard RCC Slabs, Beams, Columns |
| M25 | 1 : 1 : 2 | 25 N/mm² @ 28 Days | Heavy Foundations, Water Tanks, Retaining Walls |
| M30 / M35 | Design Mix (Automated RMC) | 30 - 35 N/mm² @ 28 Days | High-Rise Buildings, Bridge Piers, Industrial Floors |